Project Brief
204 Second Avenue is a twelve story Verizon network building in Manhattan, full of switches and telecom equipment, cooled by a two chiller plant on the first floor and heated from district steam. KeRi was retained to study replacing the primary chiller, then to design the replacement.
The survey found a plant running on one leg. The primary machine was a 670 ton York steam absorption chiller, around thirty years old, and it was out of service: the steam control valve had failed, the solution and refrigerant pumps had failed, and spare parts for its control board were no longer available. The building was being carried entirely by what was supposed to be the standby, a five year old 670 ton Trane electric centrifugal, with nothing behind it if that machine went down.
Because the building falls under New York City Local Law 97, KeRi measured the options in carbon rather than in energy cost alone. Replacing the absorption chiller with a new 670 ton electric centrifugal came out at a 725 tCO2e annual reduction for about $1.25M. Simply reversing the roles of the two existing machines gave 242 tCO2e. A 600 ton modular electric chiller gave 579 tCO2e and removed the need for a licensed operator under the city fire code, but cost more. The gap behind all three numbers is efficiency: 0.33 kW per ton for an electric machine against 2.66 for the absorption chiller.
Alongside the chiller, KeRi recommended variable frequency drives on the chilled and condenser water pumps to convert the plant to variable flow, cooling tower repairs with new isolation valves and basin heaters, and a single interlocked power feed serving whichever chiller runs, replacing the existing 800 amp disconnect with a double throw switch. The recommendation went forward into a full design that also replaced a third floor network air handler, added seventh floor economizer fans, and carried new basement supply and exhaust fans, with KeRi staying through bid, submittals, and construction administration.
MEP Engineering Scope

What We Engineered
Feasibility study and replacement design for the plant:
- Field survey and condition assessment of both chillers and the distribution
- Three replacement options modelled and priced, each measured in tCO2e
- 670 ton electric chiller replacement carried into design
- Variable frequency drives converting the plant to variable flow
- Single interlocked power feed serving whichever chiller operates
- Network air handler, economizer fans, and basement fans in the same package
Study, Then Design
01What the Survey Found
- Two 670 ton chillers on the first floor: a York steam absorption machine as primary and a Trane electric centrifugal as standby
- The absorption chiller was roughly 30 years old and out of service, with a failed steam control valve, failed solution and refrigerant pumps, and a control board whose spare parts were no longer available
- The five year old standby electric chiller was carrying the entire building alone, with no real redundancy behind it
- Four Marley cooling towers on the seventh floor, of which only two run at once, with free cooling through a plate heat exchanger below 50 degrees
- Constant volume chilled water distribution, two way valves at the air handlers, and a full size bypass able to pass the entire system flow
- Absorption chiller pumps at 1,557 GPM and 2,400 GPM with no variable frequency drives
02Three Options, Measured in Carbon
- Replace with a 670 ton electric centrifugal chiller: a reduction of 725 tCO2e per year against Local Law 97, at roughly $1.25M
- Reverse the roles, running the existing electric chiller as primary: 242 tCO2e, at roughly $1.5M including an operating engineer's salary
- Replace with a 600 ton modular electric chiller: 579 tCO2e, at roughly $2M, with no licensed operator required under the city fire code once each circuit falls below 50 HP
- Every option was modelled from measured performance and estimated operating hours, not from nameplate assumptions
- The efficiency gap drove all three: 0.3295 kW per ton for the electric chiller against 2.66 kW per ton for the absorption machine
03Plant and Electrical Recommendations
- New variable frequency drives on the chilled water and condenser water pumps, converting the plant from constant to variable flow
- Cooling tower leak repairs, new isolation valves, and new electric basin heaters for freeze protection
- Pneumatic control valves rolled into the separate building management system upgrade
- A single power feed serving both chillers, replacing the existing 800 amp disconnect with an 800 amp interlocked double throw switch, since only one chiller ever runs
- The redundant absorption chiller feed removed back to source, and pump starters replaced with drives
04Carried Into Design
- The study recommendation went forward into a full replacement design covering the chiller, the pumps, and the drives
- A third floor network air handling unit replacement and new seventh floor economizer fans were designed alongside it
- New basement supply and exhaust fans, and the interlocked double throw switch, carried into the same package
- Asbestos survey, energy code compliance, specifications, and peer review comments all carried through the design
- KeRi remained through bid RFIs, submittals, and construction administration
The Challenge
The primary chiller in a twelve story Manhattan network building had failed and could not be economically repaired, leaving the entire load on a machine meant to be the standby. Anything installed in its place had to go into a live building that cannot lose cooling, and because the building falls under New York City Local Law 97, the decision could not be made on energy cost alone. Carbon tonnage was the number that mattered, and the three credible options differed by a factor of three.
Our Solution
KeRi surveyed the plant, verified capacities with the manufacturers, and modelled three independent options from measured performance and real operating hours, pricing each and stating its carbon reduction against Local Law 97 so the choice could be made on the governing metric. The recommended route, a new 670 ton electric centrifugal, cuts roughly 725 tCO2e a year and restores genuine redundancy, and was carried into a design that also converted the pumps to variable flow, put both chillers on one interlocked feed, and replaced a network air handler and the economizer fans in the same package.
Previous Project Verizon Energy / LL97 Program Next Project Verizon DC Cooling Upgrade
