Project Brief
165 Halsey Street in Newark is a carrier hotel, and zColo, a Zayo Group company, runs colocation suites across its fifth floor. Those suites are cooled by 31 Liebert CRAC units, 8 to 30 tons each and installed between 1998 and 2010, all rejecting heat through a glycol loop to dry coolers on the roof. KeRi was brought in by Boon Energy, the owner's energy consultant, first to find out why the system was not holding up and then to fix it.
The first phase was diagnosis. The roof condenser water system had never been documented, so KeRi drew the existing conditions, inventoried every CRAC unit by tag, model, capacity, and install date, reviewed the dry-cooler selections against what was actually connected, and totalled the load: 652 tons of nominal CRAC capacity moving 2,056 GPM and pushing 8,856,960 BTU/hr, about 738 tons, back to the roof. KeRi then wrote the balancing requirements and had the loop tested against them. The report told the story: units designed for 67 GPM were measuring 38 to 46, one balancing port was blocked outright, and several had no usable flow curve.
The fix was a rebuilt pump room. New 6 inch condenser water supply and return tied into the existing 8 inch mains, an 816 GPM air separator on its own service bypass so it can be maintained without draining the loop, a new bladder expansion tank, a reduced pressure zone backflow preventer on the make-up water, and epoxy containment rolled 6 inches up the wall with a sump pump in case a pump ever leaks. The eleven roof dry coolers, 80 to 240 GPM each, were tied together on 8 inch glycol mains with differential pressure sensing, and every unit, pump, and dry cooler was to be re-balanced to its design flow.
None of it could stop the floor. The drawings say so in as many words: system shut down is not allowed. So the set carries a ten step sequence. The new piping and air separator were prefabricated complete with isolation valves before anything existing was opened, the plant ran on its backup pumps while the primary pumps were isolated, every isolation valve was exercised and proven before anyone relied on it, and strainers were cleaned one pump at a time so the loop never lost more than a single pump. Controls were integrated back to the landlord's building management system.
MEP Engineering Scope

What We Engineered
Condenser water and dry-cooler engineering for the colocation floor:
- Existing conditions documentation for the roof condenser water system
- Full CRAC and dry-cooler inventory with heat rejection totalled across the floor
- Water flow balancing requirements, specifications, and independent hydronic testing
- Rebuilt pump room with air separator, expansion tank, backflow prevention, and leak containment
- A ten step construction sequence that kept the plant running throughout
- Controls integrated to the landlord's building management system, with commissioning and training
How the Work Ran
01Existing Conditions & Analysis
- Existing conditions drawings developed for the roof condenser water system, which had never been documented as built
- Every CRAC unit inventoried by tag, model, capacity, and install date, then matched to published manufacturer performance
- Dry-cooler specifications reviewed against the connected load, unit by unit
- Heat rejection totalled across the floor: 652 tons nominal of CRAC, 6,930,600 BTU/hr of cooling, and 8,856,960 BTU/hr carried back to the dry-cooler loop
- System operation reviewed and written recommendations issued to the owner
02Glycol Distribution & Balancing
- Water flow balancing requirements and specifications written for the whole loop
- An independent hydronic test report taken against those requirements, unit by unit, which found several CRACs running far under design flow and one balancing port blocked outright
- Design flow rates carried onto the drawings at every unit so the readings had something to be measured against
- Balancing valves and butterfly valves specified at each CRAC connection, with differential pressure sensors on the mains
- Instruction to re-balance every AC unit, pump, and roof dry cooler back to its design water flow rate
03Pump Room Rebuild
- New 6 inch condenser water supply and return tied into the existing 8 inch mains, with a 1-1/2 inch connection left capped for future use
- New air separator sized at 816 GPM and 125 psig, on a service bypass line so it can be maintained without draining the loop
- New bladder expansion tank with pressure relief valve, gauge, and drain connection
- Reduced pressure zone backflow preventer on the make-up water connection
- Epoxy containment flooring rolled 6 inches up the wall around the pumps, with a sump pump piped to the nearest drain in case of a leak
- Seismic bracing on the air separator and expansion tank
04Sequencing a Live Plant
- The drawings state it plainly: system shut down is not allowed
- A ten step construction sequence written into the set, starting with prefabricating the new piping and air separator complete with isolation valves before anything existing was touched
- The plant switched onto its backup pumps while the primary pumps were isolated and the new work was cut in
- Isolation valves exercised and proven before any of them were relied on, with temporary leak protection staged in case they did not hold
- Strainers cleaned one pump at a time so the loop never lost more than a single pump
- The owner switched back to the primary pumps only once the new piping was complete and the strainers were clean
05Controls & Construction Administration
- Control sequence developed with the owner's energy consultant and a new automatic temperature control system integrated back to the landlord's central building management system
- DDC control, programming, and commissioning specified, with operator training and O&M manuals required at turnover
- Shop drawing and submittal review through construction, including the air separator, expansion tank, and hydronic specialties
- Field observation reports issued during installation
- Full piping, valve, insulation, and testing specifications carried on the drawings
The Challenge
A colocation floor cannot go warm. Thirty-one CRAC units spanning twelve years of installations were all rejecting heat to one glycol loop and a roof full of dry coolers, and the system was not keeping up, but nobody had documentation of what was actually up there. Testing showed units drawing well under their design flow, one balancing port blocked, and several units with no usable flow curve. Whatever the fix turned out to be, it had to be installed around tenants whose cabinets could not be allowed to lose cooling, and the drawings carried the constraint in plain words: system shut down is not allowed.
Our Solution
KeRi documented the plant first, inventorying every CRAC unit and dry cooler and totalling 8,856,960 BTU/hr of heat rejection so the loop could be judged against a real number rather than an assumption, then wrote balancing requirements and had the system independently tested against them. The rebuild that followed replaced the pump room piping with a new air separator on a maintenance bypass, an expansion tank, backflow prevention, and epoxy leak containment, tied the eleven roof dry coolers together on 8 inch mains with differential pressure sensing, and put every unit back to its design flow. The whole installation was sequenced in ten steps around the live floor: prefabricate first, run on backup pumps, prove every isolation valve before trusting it, and clean strainers one pump at a time.
Previous Project URvet Care Clinics Next Project zColo Chicago Suite 142
